The Chairman provided opening remarks.
The Alternate Co-Chairman for the United
States Section passed along the United
States Co-Chairman’s regrets for not being
able to attend the meeting due to other
pressing business. The Board welcomed
Lieutenant Colonel Jeffrey Hall as the new
Regulation Representative for the United
States Section. LTC Hall succeeds LTC Glen
DeWillie whom the Board thanked and wished
well in his future endeavours.
The Agenda was reviewed and revised. The
final Agenda is attached.
Agenda Item 1 – Approve Minutes of
Board Meetings on 19-20 March 2002 and
9 April 2002
This was a carry over item from previous
meetings where time constraints did not
allow for the review of the minutes. The
draft minutes of the 19-20 March 2002 were
reviewed and approved with minor revisions.
The 9 April 2002 minutes were approved
without change. The Secretaries would
prepare and issue the final minutes.
The Board concluded that, in order to
meet the requirements of the IJC’s
directive regarding the posting of Board
minutes on the web, it was necessary to
expedite the Board’s approval of the
minutes. The Board decided that, henceforth,
minutes would be reviewed and approved
through an e-mail process. Draft minutes
would be issued within one week of the
meeting and Board members and associates
would have one week to comment. A second
draft would be issued within a few days and
there would be a final one-week period to
comment.
Agenda Item 2 – Current Conditions and
Regulation Strategy
The Regulation Representatives presented
the current hydrologic conditions in the
Great Lakes-St. Lawrence River Basin. In
summary, the levels of all of the Great
Lakes were below average but above the
levels of mid-September last year. The
levels in Lac St. Louis and Montreal
Harbour were well below average but, again,
above those of last year. Precipitation in
the Great Lakes Basin had been above average
this year until mid June when it fell below
average throughout the basin. The Lake Erie
and Lake Ontario basins have been very dry
since mid-July. On 15 September, the
Lake Ontario level was at 74.64 m
(244.88 ft), 10 cm (4 in) below long
term average and 3 cm (1 in) higher than a
year ago. As a net result of the Board’s
previous outflow strategies, the level of
Lake Ontario on 15 September 2002 was 0.40
cm (0.1 in) below the level that would have
obtained if the outflows from Lake Ontario
had followed the computed Plan outflows.
If supplies over the next 6 months were
average, Lake Ontario’s level would remain
slightly below the average while Lac St.
Louis and Montreal Harbour levels would
remain well below average. Under continued
very dry conditions, Lake Ontario would fall
well below average and, by November, could
approach the low limit specified in the IJC
Orders of Approval. With these dry
conditions, Lac St. Louis would drop below
the minimum depth required for Seaway
navigation and Montreal Harbour would remain
well below chart datum throughout the fall
and early winter. Under very wet conditions,
Lake Ontario, Lac St. Louis and Montreal
Harbour would rise above average in
September.
The Board reviewed these conditions as
well as other relevant information related
to the situation of the various interests in
the system. In particular, the Board
discussed the recurring issue of the
definition of the critical needs of
navigation and power generation. The Board
decided that conditions warranted the
application of its limited discretionary
authority to deviate from the computed Plan
outflows, in order to assist the downstream
interests affected by the current dry
conditions if this could be done without
causing appreciable harm to other interests.
The Board decided on the following Lake
Ontario outflow regulation strategy:
Outflows would be in accordance with
Plan 1958-D except that a maximum weekly
over-discharge of 300 m3/s
(10 600 cfs) and no more than 600 m3/s/day
(21 200 cfs/day) above plan
would be released as required for the
following purposes:
- Ensure Montreal Harbour is at least
chart datum when required by deep
draft ship arrivals and departures.
- Maintain at least 20.6 m (67.58
feet) on Lac St. Louis.
- Ensure outflow increases to meet
critical hydropower needs.
The total maximum allowable outflow
increases for the above purposes shall
be the equivalent of 8 cm (3 in) of
water off Lake Ontario relative to Plan
1958-D. The strategy also allows for
less than Plan 1958-D specified outflows
if downstream conditions are favourable
to do so. The strategy will be reviewed
should accumulated over-discharges reach
the equivalent of 5 cm (2 in) below Plan
level, but in any event no later than
early December.
The Board will continue to closely
monitor conditions in the Lake
Ontario-St. Lawrence River System
and intervene as required.
The Board decided to further discuss the
critical needs of the hydropower and
navigation interests at its next meeting.
The purpose would be to help the Board
establish regulation strategies that are
appropriate to current circumstances.
Agenda Item 3 – Status of Lake Ontario–St.
Lawrence River Study Board
Two members of the St. Lawrence River
Board of Control are also full members of
the IJC’s Lake Ontario-St. Lawrence River
Study Board. These members provide the
Control Board with regular updates on the
progress of the Study. A brief update was
provided at this meeting.
Agenda Item 4 – Joint Control Board–Study
Board Public Meeting
The Board reviewed and agreed with the
process and protocols for the joint public
meeting that were recommended by the
Communications Committee.
Agenda Item 5 – Approval of 98th
Semi-Annual Progress Report to the IJC
Comments by members and associates had
been incorporated and coordinated prior to
the meeting. The Board reviewed key
revisions proposed subsequent to the
circulation of the current draft. The
Secretaries will finalize the report and
submit it to the IJC by the
20 September deadline requested by the
IJC.
It was agreed that the St. Lawrence River
Board of Control would join with the other
two Great Lakes Boards of Control in a
coordinated response to the IJC’s request
for an update on security matters discussed
with the boards six months ago. The Board’s
response would be provided at the
Semi-Annual Meeting in October. The response
will address any additional comments the
Boards may have concerning the responses of
the operating agencies to security concerns
as well as the Boards’ own contingency
plans.
Agenda Item 6 – Other Business
- Iroquois Dam Water Level Analysis
The Board received a briefing on the
results of studies carried out by Ontario
Power Generation (OPG) on the effect of the
operation of Iroquois Dam on the levels of
the upper St. Lawrence River. The study was
undertaken in response to user group
requests, notably the International Water
Levels Coalition, to use Iroquois Dam to
raise water levels on the upper St. Lawrence
River. Earlier studies by the power entities
concluded that dipping the gates of the dam
had no effect on levels on the river
upstream of the dam and on Lake Ontario but
caused significant head losses below the
dam. The current study employed temporary
water level gauges to gather data to compare
to the earlier findings. The results
indicated that there was no lasting effect
from use of Iroquois Dam if the flow and
Lake Ontario level remain the same. It
showed that the level of the river upstream
of the dam is dependent on the flow and the
level of Lake Ontario at Kingston.
Therefore, it was confirmed that Iroquois
Dam is not effective in raising water levels
on the upper river. OPG offered to submit a
report to the Board, for the Board’s use
in addressing the public concerns raised.
- Interim Turbine Rating Tables
This item was deferred to the next
meeting when there will be a short
briefing on turbine ratings at the
Saunders/FDR structure.
- Summer 2002 Hydropower Demand
Ontario Power Generation (OPG) and the
New York Power Authority (NYPA) provided a
summary of the hydropower demand over the
summer. The extra demand this summer was
the result of 24 days of 30 degree Celsius
(86 degrees Fahrenheit) or greater
temperatures. A "level of alert"
was declared on 23 of those days and on 9
occasions "energy emergencies"
led to requests for over discharges above
the outflow specified by the Regulation
Plan. The Board was advised that further
information on power demand can be found
on the electrical market regulators’ web
sites at:
<http:/www.theimo.com/imoweb/marketdata/marketToday.asp>
for OPG and <http:/www.nyiso.com/>
for NYPA.
- Status of USACE Great Lakes Navigation
System Review
The Board was informed that the U. S.
Army Corps of Engineers (USACE)
Reconnaissance Report was submitted to its
Headquarters for review. If approved, the
next step would be a full feasibility
study of the options. The Canadian
Government has been approached to
participate in the studies and is
currently considering its position.
- Proposals to Facilitate Rapid Response
to Changing Conditions
To facilitate the Board’s response to
changing conditions, it was decided to
schedule monthly Board teleconferences,
using them when conditions or trends
indicate. The Secretaries will develop a
schedule for consideration at the next
meeting. These conference calls will be in
addition to the conference calls that take
place from time to time under the Board’s
standard operating procedure.
- Power Entities Annual Peaking and
Ponding Report
The Power Entities submitted to the
Board their report entitled Report to the
International St. Lawrence River
Board of Control on Peaking and Ponding
Operation for the Reporting Period of
2001.
- Regulation Representatives’ Monthly
Letter
The Board asked the Regulation
Representatives to provide additional data
in the monthly letter concerning projected
supplies above or below those of the past.
This is used to help define an approaching
Criterion k situation.
Agenda Item 7 – Next Meeting and Fall
Appearance Before IJC
The next meeting of the Board was
scheduled for 9 October 2002 in Ottawa,
Ontario.
The Board was scheduled to appear before
the IJC on 8 October 2002 at 1100 hrs.
The Spring meeting of the Board was
tentatively scheduled for 5-6 March 2003 in
Chicago, Illinois.
The meeting adjourned at 1600 hrs.